Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 5 | 5 | 0.000 | 5 | 0.000 | 0.000 |
3W712 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : E File No 39751
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
144.51
Resanction Cost :
144.51
Tentative Cost :
144.51
Exp. Upto Last Fy : 0.10
For CFY 2024-2025
Remaining : 144.41
Demand : 64.00
Allotment : 18.04
Exp in CFY : 17.84
Total Up to Date Exp : 17.94
Construction Started
Physical Progress:
At start of FY 2024-2025 : 10 %
Up to Date : 60 %
Sanction on :
9 months 4 days ago
13 Oct 2023
Tentative Completion date:
8 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
3.00 किमी0 लम्बाई में पहाड़ कटान का कार्य पूर्ण। अवशेष कार्य प्रगति पर। -- as on 03-Jul-2024