Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 5 | 5 | 5 | 0 |
3W712 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : E File No 39751
TS Amount (lakhs) : 0 Lacs
Financial Detail
Sanction Cost : 144.51 Lacs
Resanction Cost : 144.51 Lacs
Exp. Upto Last Fy : 0.10 Lacs
For CFY 2024-2025
Remaining : 144.41 Lacs
Demand : 64.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 0.10 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 10 %
Up to Date : 10 %
Sanction on :
7 months 6 days ago
13 Oct 2023
Tentative Completion date:
10 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
पहाड़ कटान का कार्य प्रगति पर। -- as on 10-Apr-2024
Physical Peramenters