Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3.45 | 3.45 | 0.000 | 3.45 | 0.000 | 0.000 |
3W713 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : E File No 60253
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
107.28
Resanction Cost :
107.28
Tentative Cost :
107.28
Exp. Upto Last Fy : 65.44
For CFY 2024-2025
Remaining : 41.84
Demand : 45.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 65.44
Construction Started
Physical Progress:
At start of FY 2024-2025 : 35 %
Up to Date : 75 %
Sanction on :
8 months 2 weeks ago
27 Oct 2023
Tentative Completion date:
1 week 6 days from now
31 Jul 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य प्रगति पर। -- as on 06-Feb-2024