Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 4.7 | 4.7 | 4.7 | 0 |
3W714 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : E File No 60714
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
258.10
Resanction Cost :
258.10
Tentative Cost :
258.10
Exp. Upto Last Fy : 56.84
For CFY 2024-2025
Remaining : 201.26
Demand : 100.00
Allotment : 120.00
Exp in CFY : 66.76
Total Up to Date Exp : 123.60
Construction Started
Physical Progress:
At start of FY 2024-2025 : 30 %
Up to Date : 85 %
Sanction on :
9 months 1 week ago
10 Oct 2023
Tentative Completion date:
1 month 1 week from now
31 Aug 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
स्कपर, दीवार, सोलिंग, इन्टर का कार्य पूर्ण। 3.00 किमी0 में पी0सी0 का कार्य पूर्ण। अवशेष कार्य प्रगति पर। -- as on 03-Jul-2024
Physical Peramenters