Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 4.17 | 4.17 | 0.000 | 4.17 | 2.670 | 0.000 |
3W733 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : E File No 48456
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
79.32
Resanction Cost :
79.32
Tentative Cost :
79.32
Exp. Upto Last Fy : 32.50
For CFY 2024-2025
Remaining : 46.82
Demand : 46.82
Allotment : 20.00
Exp in CFY : 23.99
Total Up to Date Exp : 56.49
Work completed
Physical Progress:
At start of FY 2024-2025 : 30 %
Up to Date : 100 %
Sanction on :
8 months 2 days ago
15 Nov 2023
Tentative Completion date:
3 months 2 weeks ago
31 Mar 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण। दायित्वों का भुगतान शेष। -- as on 07-Jun-2024