Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 4.17 | 4.17 | 0.000 | 4.17 | 2.670 | 0.000 |
3W733 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : E File No 48456
TS Amount (lakhs) : 0 Lacs
Financial Detail
Sanction Cost : 79.32 Lacs
Resanction Cost : 79.32 Lacs
Exp. Upto Last Fy : 32.50 Lacs
For CFY 2024-2025
Remaining : 46.82 Lacs
Demand : 46.82 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 32.50 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 30 %
Up to Date : 30 %
Sanction on :
6 months 4 days ago
15 Nov 2023
Tentative Completion date:
1 month 2 weeks ago
31 Mar 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
सुरक्षा दिवार निर्माण का कार्य प्रगति पर -- as on 13-Feb-2024
Physical Peramenters