Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 87.6 | 87.6 | 87.6 | 0 |
3W751 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 4088/।।।(2)/2023-(प्रा0आ0)/2023
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
181.86
Resanction Cost :
181.86
Tentative Cost :
181.86
Exp. Upto Last Fy : 72.44
For CFY 2024-2025
Remaining : 109.42
Demand : 109.42
Allotment : 0.00
Exp in CFY : 26.84
Total Up to Date Exp : 99.28
Construction Started
Physical Progress:
At start of FY 2024-2025 : 15 %
Up to Date : 90 %
Sanction on :
8 months 2 weeks ago
01 Nov 2023
Tentative Completion date:
1 month 1 week from now
31 Aug 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कै्रश बैरियर लगाये जाने का कार्य पूर्ण। क्राशेनरी बोर्ड लगाये जाने का कार्य प्रगति पर। -- as on 29-Jun-2024
Physical Peramenters