Work Profile Report [3W751]
Tenders
Project Activities
alerts
Administrative Approval Detail : 4088/।।।(2)/2023-(प्रा0आ0)/2023
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : सड़क सुरक्षा कार्य ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
181.86
Resanction Cost :
181.86
Tentative Cost :
181.86
Exp. Upto Last Fy :
72.44
For CFY 2024-2025
Remaining :
109.42
Demand :
109.42
Allotment :
100.00
Exp in CFY :
71.88
Total Up to Date Exp :
144.32
Construction Started
Sanction on : 1 year 3 weeks ago
01 Nov 2023
Physical Progress:
At start of FY 2024-2025 :
15 %
Up to Date :
90 %
Tentative Completion date on : 2 months 3 weeks ago
31 Aug 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कै्रश बैरियर लगाये जाने का कार्य पूर्ण। क्राशेनरी बोर्ड लगाये जाने का कार्य प्रगति पर। -- as on 29-Jun-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand