Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 60.59 | 60.59 | 60.59 | 0 |
3W752 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 4088/।।।(2)/2023-(प्रा0आ0)/2023
TS Amount (lakhs) : 0 Lacs
Financial Detail
Sanction Cost : 95.39 Lacs
Resanction Cost : 95.39 Lacs
Exp. Upto Last Fy : 90.49 Lacs
For CFY 2024-2025
Remaining : 4.90 Lacs
Demand : 4.90 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 90.49 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 15 %
Up to Date : 15 %
Sanction on :
6 months 2 weeks ago
01 Nov 2023
Tentative Completion date:
1 month 2 weeks ago
31 Mar 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य प्रगति पर। -- as on 06-Feb-2024
Physical Peramenters