Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 208.38 | 208.38 | 208.38 | 0 |
3W753 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 4088/।।।(2)/2023-(प्रा0आ0)/2023
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
233.23
Resanction Cost :
233.23
Tentative Cost :
233.23
Exp. Upto Last Fy : 107.00
For CFY 2024-2025
Remaining : 126.23
Demand : 126.23
Allotment : 0.00
Exp in CFY : 36.55
Total Up to Date Exp : 143.55
Construction Started
Physical Progress:
At start of FY 2024-2025 : 25 %
Up to Date : 93 %
Sanction on :
8 months 2 weeks ago
01 Nov 2023
Tentative Completion date:
1 month 1 week from now
31 Aug 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
3615 मीटर में कै्रश बैरियर लगाये जाने का कार्य पूर्ण। अवशेष कार्य प्रगति पर। -- as on 29-Jun-2024
Physical Peramenters