Administrative Approval Detail : E File No- 56385
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : Not Available
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
1414.25
Resanction Cost :
1414.25
Tentative Cost :
1414.25
Exp. Upto Last Fy :
1,400.58
For CFY 2025-2026
Remaining :
13.67
Demand :
0.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
1,400.58
Construction Started
Sanction on : 1 year 3 months ago
15 Mar 2024
Physical Progress:
At start of FY 2025-2026 :
100 %
Up to Date :
100 %
Tentative Completion date on : 3 months 1 week ago
31 Mar 2025
Actual Completion Date : 3 months 3 weeks ago
18 Mar 2025
Physical Linear Components
Remark
कार्य पूर्ण। -- as on 11-Apr-2025