Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 17 | 14.5 | 14.5 | 0 |
3W85 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा.सं. 299लो.नि.-2/2004-16(प्रा.आ.)/04 दि. 28.02.04
TS Amount (lakhs) : 301 Lacs
Financial Detail
Sanction Cost : 301.00 Lacs
Resanction Cost : 301.00 Lacs
Exp. Upto Last Fy : 261.46 Lacs
For CFY 2024-2025
Remaining : 39.54 Lacs
Demand : 39.54 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 261.46 Lacs
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
20 years 2 months ago
28 Feb 2004
Tentative Completion date:
1 year 10 months from now
31 Mar 2026
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 13: AIP DFO
Bottelneck: no issue
1. स्वीकृत लागत के अन्तर्गत कार्य पूर्णं पुनरीक्षित आगणन गठित कर प्रेषित।
2. मुआवजा प्रस्ताव गठन हेतु गठित अनुबन्ध संख्या-98/ए.ई.-।।। दिनांक 16.01.2024 द्वारा गठित। जिसके अन्तर्गत अमीन द्वारा कार्यस्थल का भ्रमण कर लिया गया है। मुआवजा प्रस्ताव गठित किया जा रहा है।
3- खण्डीय कार्यालय के पत्रांक पत्रांक 4486/36सी. दिनांक 05.12.2023 को अनुपालन आख्या प्रभागीय वनाधिकारी, अल्मोड़ा को प्रेषित।
-- as on 28-Apr-2024
Physical Peramenters