Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 7 | 0 | 0 | 0 |
3W93 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा.सं. 2454/111-2/05-07 (प्रा.आ.)/05 टी.सी.-। दि. 28.10.05
TS Amount (lakhs) : 160.22 Lacs
Financial Detail
Sanction Cost : 160.22 Lacs
Resanction Cost : 160.22 Lacs
Exp. Upto Last Fy : 80.47 Lacs
For CFY 2024-2025
Remaining : 79.75 Lacs
Demand : 10.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 80.47 Lacs
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
18 years 6 months ago
28 Oct 2005
Tentative Completion date:
10 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
मुआवजा प्रस्ताव गठित। सत्यापन उपरान्त भुगतान किया जायेगा। -- as on 10-Apr-2024
Physical Peramenters