Work Profile Report [3W98]
Tenders
Project Activities
Samples
Administrative Approval Detail : शा.सं. 2491/111(2)/06-36 (प्रा.आ.)/06 दि. 19.09.06
TS Amount (lakhs) : 409.5 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
409.50
Resanction Cost :
409.50
Tentative Cost :
316.71
Saving
92.79
Exp. Upto Last Fy :
252.98
For CFY 2025-2026
Remaining :
156.52
Demand :
2.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
252.98
Construction Started
Sanction on : 19 years 1 month ago
19 Sep 2006
Physical Progress:
At start of FY 2025-2026 :
85 %
Up to Date :
85 %
Tentative Completion date on : 1 year 7 months from now
30 Jun 2027
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
पुनः क्षतिपूरक वृक्षारोपण स्थल का कब्जा दिनांक 19.11.2025 को वन क्षेत्राधिकारी, रानीखेत को दिया जाना है। -- as on 14-Nov-2025
© 2025 PWD Uttarakhand