Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 18 | 16.2 | 5.420 | 10.78 | 0.000 | 0.000 |
3W98 :
Administrative Approval Detail : शा.सं. 2491/111(2)/06-36 (प्रा.आ.)/06 दि. 19.09.06
TS Amount (lakhs) : 409.5 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
409.50
Resanction Cost :
409.50
Tentative Cost :
409.50
Exp. Upto Last Fy : 250.89
For CFY 2024-2025
Remaining : 158.61
Demand : 20.00
Allotment : 0.51
Exp in CFY : 0.50
Total Up to Date Exp : 251.39
Construction Started
Physical Progress:
At start of FY 2024-2025 : 85 %
Up to Date : 85 %
Sanction on :
17 years 9 months ago
19 Sep 2006
Tentative Completion date:
1 year 8 months from now
31 Mar 2026
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 13: AIP DFO
Bottelneck: Sanction Required form Govt
1- 14.20 किमी0 लम्बाई के सापेक्ष 5.20 किमी0 लम्बाई में मार्ग निर्माण का कार्य पूर्ण। अवशेष कार्य हेतु पुनरीक्षित आगणन गठित कर प्रेषित।
2- अनुपालन आख्या इस कार्यालय के पत्रांक 4255/36सी दिनांक 01-11-2023 द्वारा प्रभागीय वनाधिकारीए अल्मोड़ा वन प्रभागए अल्मोड़ा को प्रेषित।
-- as on 28-Apr-2024
Physical Peramenters