Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 9 | 6.32 | 6.32 | 0 |
3W99 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा.सं. 2491/111(2)/06-36 (प्रा.आ.)/06 दि. 19.07.06
TS Amount (lakhs) : 160.2 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
160.20
Resanction Cost :
160.20
Tentative Cost :
160.20
Exp. Upto Last Fy : 108.59
For CFY 2024-2025
Remaining : 51.61
Demand : 10.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 108.59
Construction Started
Physical Progress:
At start of FY 2024-2025 : 76 %
Up to Date : 76 %
Sanction on :
17 years 11 months ago
19 Jul 2006
Tentative Completion date:
8 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 13: AIP DFO
Bottelneck: Sanction Required form Govt
1- 6.32 किमी0 लम्बाई के सापेक्ष 4.00 किमी0 लम्बाई में मार्ग निर्माण का कार्य पूर्ण। अवशेष कार्य हेतु पुनरीक्षित आगणन गठित कर प्रेषित।
2- अनुपालन आख्या इस कार्यालय के पत्रांक 4326/36सी. दिनांक 17.11.2023 द्वारा प्रभागीय वनाधिकारी, अल्मोड़ा वन प्रभाग, अल्मोड़ा को प्रेषित।
-- as on 28-Apr-2024
Physical Peramenters