Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1 | 1 | 1 | 0 |
40W21 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 2300/।।।(2)/08-42 प्रा0आ0/07टी॰सी॰- दिनांक 4.7.08
TS Amount (lakhs) : 0 Lacs
Financial Detail
Sanction Cost : 36.75 Lacs
Resanction Cost : 36.75 Lacs
Exp. Upto Last Fy : 25.29 Lacs
For CFY 2024-2025
Remaining : 11.46 Lacs
Demand : 11.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 25.29 Lacs
Work completed
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 0 %
Sanction on :
15 years 10 months ago
04 Jul 2008
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Forest Status ---
Bottelneck: no issue
कार्य पूर्ण। -- as on 23-Apr-2023
Physical Peramenters