Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 8 | 8 | 0.000 | 8 | 0.000 | 0.000 |
No of Bridges | 2 | 2 | 0 | 2 | 0 | 0 |
40W231 :
Work not linked with IM
Roads on The Basis of AI: Road 1
Bridges on The Basis of AI: Argad Gadera Bridge
Administrative Approval Detail : शा॰सं॰ 2189(1)/।।।(2) 13-60(प्रा॰आ॰)/2012 दिनंाक 22-03-2013
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
102.62
Resanction Cost :
102.62
Tentative Cost :
102.62
Exp. Upto Last Fy : 57.04
For CFY 2024-2025
Remaining : 45.58
Demand : 6.00
Allotment : 1.00
Exp in CFY : 0.05
Total Up to Date Exp : 57.09
Work completed
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 0 %
Sanction on :
11 years 3 months ago
22 Mar 2013
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 18: Final Approval
Bottelneck: no issue
कुछ काश्तकारों को मुआवजा वितरण किया जा चुका है। अवशेष काश्तकारों को मआवजा वितरण की कार्यवाही गतिमान है। -- as on 22-Apr-2023
Physical Peramenters