Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1 | 0.32 | 0.32 | 0 |
Closed Work 40W26 :
Administrative Approval Detail : 2490/।।।-2/2008-61ड्ढ{)प्राड्ढ{)आड्ढ{)/07 दिनांक 25.8.09
TS Amount (lakhs) : 9.07 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
28.35
Resanction Cost :
28.35
Tentative Cost :
28.35
Exp. Upto Last Fy : 20.43
For CFY 2024-2025
Remaining : 7.92
Demand : 0.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 20.43
Work completed
Physical Progress:
At start of FY 2024-2025 : 66 %
Up to Date : 0 %
Sanction on :
15 years 10 months ago
25 Aug 2008
Tentative Completion date:
12 years 3 months ago
31 Mar 2012
Actual Completion Date:
13 years 2 weeks ago
01 Jul 2011
Remark
Bottelneck: no issue
कार्य पूर्ण।
Physical Peramenters