Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 8.55 | 8.55 | 8.55 | 0 |
40W267 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा॰सं॰ 1055/।।। (2) /14 -17(प्रा॰आ॰)/2013 दिनांक 04-03-2014
TS Amount (lakhs) : 1135.87 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
1135.87
Resanction Cost :
1135.87
Tentative Cost :
1135.87
Exp. Upto Last Fy : 1,119.99
For CFY 2024-2025
Remaining : 15.88
Demand : 8.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 1,119.99
Work completed
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 0 %
Sanction on :
10 years 4 months ago
04 Mar 2014
Tentative Completion date:
7 years 3 months ago
31 Mar 2017
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण। अवशेष धनराशि के अन्तर्गत मुआवजा वितरण की कार्यवाही गतिमान है। -- as on 31-Jul-2020
Physical Peramenters