Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 7 | 0 | 0 | 0 | ||
No of Bridges | 3 | 3 | 3 | 0 |
40W294 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा॰सं॰ 2724/।।।(2)/15-05 (मु॰मं॰घो॰)/15 दिनंाक 23-04-2015
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
71.72
Resanction Cost :
71.72
Tentative Cost :
71.72
Exp. Upto Last Fy : 0.10
For CFY 2024-2025
Remaining : 71.62
Demand : 2.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 0.10
Unstarted Work
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 0 %
Sanction on :
9 years 2 months ago
23 Apr 2015
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: Alignment Dispute
सर्वेक्षण कार्य करते समय ग्रामीणों द्वारा विवाद किया जा रहा है विवाद सुलझाने हेतु पुनः इस कार्यालय का पत्र सं॰ 897/1सी॰ दिनंाक 25-04-2022 द्वारा उपजिलाधिकारी, ऊखीमठ को पत्र लिखा गया है। पुनः माह अपै्रल, 2023 में सर्वे कार्य करवाया गया है। ग्रामीणों द्वारा भूमि भूमि देने हेतु सहमति का प्रयास जारी है। -- as on 22-Apr-2023
Physical Peramenters