Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 6 | 6 | 0.000 | 6 | 0.000 | 0.000 |
No of Bridges | 1 | 1 | 0 | 1 | 0 | 0 |
Span of Bridges [m] | 90 | 90 | 0.000 | 90 | 0.000 | 0.000 |
40W332 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा॰सं॰ 1156/।।।(2)/16-07 (एम॰एल॰ए॰) /2015 दिनंाक 29-02-2016
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
34.80
Resanction Cost :
34.80
Tentative Cost :
34.80
Exp. Upto Last Fy : 2.29
For CFY 2024-2025
Remaining : 32.51
Demand : 2.00
Allotment : 1.00
Exp in CFY : 0.07
Total Up to Date Exp : 2.36
Unstarted Work
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 0 %
Sanction on :
8 years 4 months ago
29 Feb 2016
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: Alignment Dispute
सर्वेक्षण कार्य माह मार्च, 2023 पूर्ण । भू-गर्भवेत्ता द्वारा सर्वेक्षण कर लिया गया है। -- as on 22-Apr-2023
Physical Peramenters