Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 5.45 | 6.62 | 5.950 | 0.67 | 0.450 | 0.000 |
40W396 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा॰सं॰ 4392(1)/।।। (2) 18-38 (प्रा॰आ॰) /2018, दिनांक 07-09-2018
TS Amount (lakhs) : 487.02 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
487.02
Resanction Cost :
487.02
Tentative Cost :
487.02
Exp. Upto Last Fy : 310.25
For CFY 2024-2025
Remaining : 176.77
Demand : 176.77
Allotment : 17.68
Exp in CFY : 9.83
Total Up to Date Exp : 320.08
Construction Started
Physical Progress:
At start of FY 2024-2025 : 80 %
Up to Date : 80 %
Sanction on :
5 years 10 months ago
07 Sep 2018
Tentative Completion date:
8 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
उक्त मोटर मार्ग की 400 मी० लम्बाई जिस पर पहाड़ कटान का शेष हें एन0 एच0 107 ठीक ऊपर स्थित हें उक्त लम्बाई में पहाड़ कटान कार्य वर्तमान में चारधाम यात्रा के कारण बंद किया गया हें चारधाम यात्रा की समाप्ति के उपरांत माह नवम्बर से पुनः कार्य शुरु किया जायेगा । -- as on 04-Jul-2024
Physical Peramenters