Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 5.45 | 6.62 | 5.950 | 0.67 | 0.450 | 0.000 |
40W396 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा॰सं॰ 4392(1)/।।। (2) 18-38 (प्रा॰आ॰) /2018, दिनांक 07-09-2018
TS Amount (lakhs) : 487.02 Lacs
Financial Detail
Sanction Cost : 487.02 Lacs
Resanction Cost : 487.02 Lacs
Exp. Upto Last Fy : 310.25 Lacs
For CFY 2024-2025
Remaining : 176.77 Lacs
Demand : 176.77 Lacs
Allotment : 17.68 Lacs
Exp in CFY : 4.80 Lacs
Total Up to Date Exp : 315.05 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 80 %
Up to Date : 80 %
Sanction on :
5 years 8 months ago
07 Sep 2018
Tentative Completion date:
10 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
एन0 एच0 के ऊपर स्थित 1.17 कि0मी0 में पहाड़ कटान कार्य प्रगति में। -- as on 06-Mar-2024
Physical Peramenters