Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3 | 3 | 0.000 | 3 | 0.000 | 0.000 |
40W397 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा॰सं॰ 5071/।।। (2) 18-38 (प्रा॰आ॰) /2018, दिनांक 15-10-2018
TS Amount (lakhs) : 239.51 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
239.51
Resanction Cost :
239.51
Tentative Cost :
239.51
Exp. Upto Last Fy : 224.89
For CFY 2024-2025
Remaining : 14.62
Demand : 14.62
Allotment : 1.00
Exp in CFY : 0.00
Total Up to Date Exp : 224.89
Work completed
Physical Progress:
At start of FY 2024-2025 : 95 %
Up to Date : 95 %
Sanction on :
5 years 9 months ago
15 Oct 2018
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
डिफेक्ट कटिंग एवं पार्ट-।। का कार्य प्रगति पर। -- as on 23-Apr-2023
Physical Peramenters