Work Profile Report [40W409]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : fजलाfधकारी, रुद्रप्रयाग का पत्रांक 334/fवfवध/2018-19 fदनांक 25-01-2019
TS Amount (lakhs) : 68.5 Lacs
Budget Financial Head : SRMD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
68.50
Resanction Cost :
68.50
Tentative Cost :
68.50
Exp. Upto Last Fy :
58.11
For CFY 2024-2025
Remaining :
10.39
Demand :
1.30
Allotment :
0.00
Exp in CFY :
0.59
Total Up to Date Exp :
58.70
Work completed
Sanction on : 5 years 9 months ago
25 Jan 2019
Physical Progress:
At start of FY 2024-2025 :
45 %
Up to Date :
95 %
Tentative Completion date on :
Yet To Decide
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
पहाड कटान पूर्ण। दीवार, सुरक्षात्मक आदि कार्य पूर्ण डिफेक्ट कटिंग /ग्रेड सुधार/दीवार निर्माण कार्य प्रगति पर। -- as on 24-Apr-2023
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand