Work Profile

जाखधार देवर मोटर मार्ग का सुधार कार्य।


Work not linked with IM

Bridges on The Basis of AI:

Administrative Approval Detail : fजला अर्थ एवं संख्याfधकारी, रुद्रप्रयाग का पत्रांक 429/fवfवध /2020-21 fदनांक 06-11-2020

TS Amount (lakhs) : 30 Lacs

Financial Detail

Sanction Cost : 30.00 Lacs

Resanction Cost : 30.00 Lacs

Exp. Upto Last Fy : 29.21 Lacs

For CFY 2024-2025

Remaining : 0.79 Lacs

Demand : 0.79 Lacs

Allotment : 0.79 Lacs

Exp in CFY : 0.22 Lacs

Total Up to Date Exp : 29.43 Lacs

Work completed

Physical Progress:

At start of FY 2024-2025 : 0 %

Up to Date : 70 %

Sanction on :
3 years 6 months ago
06 Nov 2020


Tentative Completion date:
Yet To Decide


Actual Completion Date:
Not Yet Reported


Rating : 98

Remark

Bottelneck: no issue


कार्य पूर्ण। दायित्व शेष। -- as on 08-Dec-2023

Physical Peramenters

Particulars Sanction Resanction Upto Last Fy For Cfy 2024-2025
Remaining Target Achievement
Length of Road [Km] 0.85 0.85 0.000 0.85 0.000 0.000
Currently only Bank Gaurantee information is avilable