Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3 | 3 | 0.000 | 3 | 0.000 | 0.000 |
40W449 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 3738(1)/।।।(2)/-35 (प्रा॰आ॰)/2017 टी॰सी॰ दिनंाक 15-09-2021
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
84.19
Resanction Cost :
84.19
Tentative Cost :
84.19
Exp. Upto Last Fy : 57.03
For CFY 2024-2025
Remaining : 27.16
Demand : 14.29
Allotment : 10.00
Exp in CFY : 0.00
Total Up to Date Exp : 57.03
Construction Started
Physical Progress:
At start of FY 2024-2025 : 73 %
Up to Date : 73 %
Sanction on :
2 years 10 months ago
15 Sep 2021
Tentative Completion date:
2 months 2 weeks ago
30 Apr 2024
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 18: Final Approval
Bottelneck: no issue
भारत सरकार के पत्र सं॰ 8बी॰/यू॰सी॰पी॰/06/133/2020/एफ॰सी॰/691 दिनांक 09-09-2021 द्वारा विधिवत् स्वीकृति प्राप्त। 2.20 कि॰मी॰ लम्बाई में पहाड कटान कार्य पूर्ण। अवशेष लम्बाई में पहाड़ कटान कार्य प्रगति पर। -- as on 30-Apr-2024
Physical Peramenters