Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 0.5 | 0.5 | 0.000 | 0.5 | 0.000 | 0.000 |
40W481 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : जिला अर्थ एवं संख्याधिकारी, रुद्रप्रयाग का पत्रांक 508/जि॰यो॰-03/2022 दिनंाक 09-09-2022
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
11.00
Resanction Cost :
11.00
Tentative Cost :
11.00
Exp. Upto Last Fy : 8.99
For CFY 2024-2025
Remaining : 2.01
Demand : 2.01
Allotment : 2.01
Exp in CFY : 0.22
Total Up to Date Exp : 9.21
Work completed
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 70 %
Sanction on :
1 year 10 months ago
09 Sep 2022
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण।दायित्व शेष। -- as on 06-May-2024
Physical Peramenters