Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
No of Bridges | 1 | 1 | 0 | 1 | 0 | 0 |
Span of Bridges [m] | 15 | 15 | 0.000 | 15 | 0.000 | 0.000 |
40W503 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : जिला अर्थ एवं संख्या अधिकारी रुद्रप्रयाग का पत्रांक 163/जिला यो॰/23-24 दिनंाक 05-06-2023
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
11.00
Resanction Cost :
11.00
Tentative Cost :
11.00
Exp. Upto Last Fy : 0.00
For CFY 2024-2025
Remaining : 11.00
Demand : 11.00
Allotment : 11.00
Exp in CFY : 3.00
Total Up to Date Exp : 3.00
Unstarted Work
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 20 %
Sanction on :
1 year 2 months ago
06 May 2023
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य प्रगति पर है। -- as on 06-May-2024
Physical Peramenters