Work Profile Report [40W510]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : जिला अर्थ एवं संख्या अधिकारी रुद्रप्रयाग का पत्रांक 163/जिला यो॰/23-24 दिनंाक 05-06-2023
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : SRMD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
4.00
Resanction Cost :
4.00
Tentative Cost :
4.00
Exp. Upto Last Fy :
2.00
For CFY 2024-2025
Remaining :
2.00
Demand :
2.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
2.00
Construction Started
Sanction on : 1 year 6 months ago
05 Jun 2023
Physical Progress:
At start of FY 2024-2025 :
30 %
Up to Date :
30 %
Tentative Completion date on :
Yet To Decide
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य प्रगति पर । -- as on 21-Feb-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: