Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Jobs | 1 | 1 | 0 | 1 | 0 | 0 |
40W528 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : जिला अर्थ एवं संख्या अधिकारी रुद्रप्रयाग का पत्रांक 163/जिला यो॰/23-24 दिनंाक 05-06-2023
TS Amount (lakhs) : 0 Lacs
Financial Detail
Sanction Cost : 22.00 Lacs
Resanction Cost : 22.00 Lacs
Exp. Upto Last Fy : 3.03 Lacs
For CFY 2024-2025
Remaining : 18.97 Lacs
Demand : 18.97 Lacs
Allotment : 14.47 Lacs
Exp in CFY : 1.51 Lacs
Total Up to Date Exp : 4.54 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 25 %
Up to Date : 35 %
Sanction on :
11 months 2 weeks ago
05 Jun 2023
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य प्रगति पर । -- as on 21-Feb-2024
Physical Peramenters