Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 7.03 | 7.03 | 0.000 | 7.03 | 0.000 | 0.000 |
40W535 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : कार्यालय प्रमुख अभियन्ता एवं विभागाध्यक्ष, लो॰नि॰वि॰, उत्तराखण्ड, देहरादून का पत्रांक 895/07याता- पी॰एम॰जी॰एस॰वाई॰-नि॰।।। दिनांक 16-05-2023
TS Amount (lakhs) : 0 Lacs
Financial Detail
Sanction Cost : 184.79 Lacs
Resanction Cost : 184.79 Lacs
Exp. Upto Last Fy : 150.21 Lacs
For CFY 2024-2025
Remaining : 34.58 Lacs
Demand : 34.58 Lacs
Allotment : 30.00 Lacs
Exp in CFY : 0.60 Lacs
Total Up to Date Exp : 150.81 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 50 %
Up to Date : 60 %
Sanction on :
1 year 3 days ago
16 May 2023
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
स्कपर एवं काॅजवे निर्माण कार्य पूर्ण। डब्लू॰बी॰एम॰ का कार्य प्रगति पर। -- as on 16-Feb-2024
Physical Peramenters