Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 7.03 | 7.03 | 0.000 | 7.03 | 0.000 | 0.000 |
40W535 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : कार्यालय प्रमुख अभियन्ता एवं विभागाध्यक्ष, लो॰नि॰वि॰, उत्तराखण्ड, देहरादून का पत्रांक 895/07याता- पी॰एम॰जी॰एस॰वाई॰-नि॰।।। दिनांक 16-05-2023
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
184.79
Resanction Cost :
184.79
Tentative Cost :
184.79
Exp. Upto Last Fy : 150.21
For CFY 2024-2025
Remaining : 34.58
Demand : 34.58
Allotment : 38.00
Exp in CFY : 37.41
Total Up to Date Exp : 187.62
Work completed
Physical Progress:
At start of FY 2024-2025 : 50 %
Up to Date : 100 %
Sanction on :
1 year 2 months ago
16 May 2023
Tentative Completion date:
2 months 2 weeks ago
30 Apr 2024
Actual Completion Date:
3 months 2 weeks ago
31 Mar 2024
Remark
Bottelneck: no issue
कार्य पूर्ण। दायित्व शेष। -- as on 01-Jun-2024