Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 18.5 | 18.5 | 0.000 | 18.5 | 0.000 | 0.000 |
40W536 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : कार्यालय प्रमुख अभियन्ता एवं विभागाध्यक्ष, लो॰नि॰वि॰, उत्तराखण्ड, देहरादून का पत्रांक 895ध्07याता- पी॰एम॰जी॰एस॰वाई॰-नि॰।।। दिनांक 16-05-2023
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
493.33
Resanction Cost :
493.33
Tentative Cost :
493.33
Exp. Upto Last Fy : 218.40
For CFY 2024-2025
Remaining : 274.93
Demand : 274.93
Allotment : 81.00
Exp in CFY : 80.14
Total Up to Date Exp : 298.54
Construction Started
Physical Progress:
At start of FY 2024-2025 : 20 %
Up to Date : 80 %
Sanction on :
1 year 2 months ago
16 May 2023
Tentative Completion date:
2 months 1 week from now
30 Sep 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
18 कि॰मी॰ लम्बाई में पी॰सी॰ कार्य पूर्ण। दीवार निर्माण, नाली निर्माण, स्कपर निर्माण कार्य प्रगति पर। -- as on 28-Jun-2024
Physical Peramenters