Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 21.5 | 21.5 | 0.000 | 21.5 | 0.000 | 0.000 |
40W540 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा॰सं॰ 2451/।।।(2)/23-01 (प्रा॰आ॰)/2019लोक निर्माण अनुभाग-2॰ दिनंाक 21-07-2023
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
260.86
Resanction Cost :
412.76
Tentative Cost :
412.76
Exp. Upto Last Fy : 183.11
For CFY 2024-2025
Remaining : 229.65
Demand : 229.65
Allotment : 156.09
Exp in CFY : 156.09
Total Up to Date Exp : 339.20
Construction Started
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 70 %
Sanction on :
11 months 3 weeks ago
21 Jul 2023
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
क्रैश बैरियर का कार्य पूर्ण। अवशेष कार्य प्रगति पर है। -- as on 01-Jun-2024
Physical Peramenters