Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 15.35 | 15.35 | 15.35 | 0 |
40W543 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : ई-फाईल संख्या 48456/140131/2023 दिनंाक 21-08-2023
TS Amount (lakhs) : 0 Lacs
Financial Detail
Sanction Cost : 427.51 Lacs
Resanction Cost : 427.51 Lacs
Exp. Upto Last Fy : 213.49 Lacs
For CFY 2024-2025
Remaining : 214.02 Lacs
Demand : 214.02 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 213.49 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 20 %
Up to Date : 20 %
Sanction on :
8 months 4 weeks ago
21 Aug 2023
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
क्रासड्रेनेज, नाली निर्माण एवं स्कपर निर्माण कार्य प्रगति पर। । -- as on 16-Feb-2024
Physical Peramenters