Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 30.01 | 30.01 | 0.000 | 30.01 | 0.000 | 0.000 |
40W546 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : उत्तराखण्ड शासन लो॰नि॰वि॰, अनुभाग-2 का पत्रांक 4088ध् ।।।(2) ध्2023 (प्रा॰आ॰)/् 2023 दिनंाक 01-11-2023
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
79.63
Resanction Cost :
79.63
Tentative Cost :
79.63
Exp. Upto Last Fy : 23.88
For CFY 2024-2025
Remaining : 55.75
Demand : 55.75
Allotment : 23.77
Exp in CFY : 23.77
Total Up to Date Exp : 47.65
Construction Started
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 70 %
Sanction on :
8 months 2 weeks ago
01 Nov 2023
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
क्रैश बैरियर का कार्य पूर्ण। अवशेष कार्य प्रगति पर है। -- as on 01-Jun-2024
Physical Peramenters