Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 7 | 7 | 7 | 0 |
40W64 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 2910/।।। (2)/09-146 (सामान्य)/07 दिनांक 03.09.09
TS Amount (lakhs) : 257.25 Lacs
Financial Detail
Sanction Cost : 257.25 Lacs
Resanction Cost : 257.25 Lacs
Exp. Upto Last Fy : 247.09 Lacs
For CFY 2024-2025
Remaining : 10.16 Lacs
Demand : 10.16 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 247.09 Lacs
Work completed
Physical Progress:
At start of FY 2024-2025 : 49 %
Up to Date : 49 %
Sanction on :
14 years 8 months ago
03 Sep 2009
Tentative Completion date:
4 years 1 month ago
31 Mar 2020
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 13: AIP DFO
Bottelneck: no issue
कार्य पूर्ण। प्रतिकर भुगतान शेष। -- as on 23-Apr-2023
Physical Peramenters