43W1028 :

No Pic Avilable Time series Gantt
सडक सुरक्षा वर्ष 2023-2024 के अन्तर्गत निराली दपोली सुनाली मोटर मार्ग पर सड़क सुरक्षा कार्य।


Work not linked with IM

Bridges on The Basis of AI:

Administrative Approval Detail : शासन का पत्रांक 5082/111(2)2023-01(प्रा0आ0)/2023 दि0 09.11.2023

TS Amount (lakhs) : 91.23 Lacs

Financial Detail (in Rs Lakhs)

Sanction Cost :

91.23

Resanction Cost :

91.23

Tentative Cost :

91.23

Exp. Upto Last Fy : 52.24

For CFY 2024-2025

Remaining : 38.99

Demand : 38.99

Allotment : 52.24

Exp in CFY : 0.00

Total Up to Date Exp : 52.24

Work completed

Physical Progress:

At start of FY 2024-2025 : 100 %

Up to Date : 100 %

Sanction on :
8 months 1 week ago
09 Nov 2023


Tentative Completion date:
4 months 2 days ago
15 Mar 2024


Actual Completion Date:
Not Yet Reported


Rating : 100

Remark

Bottelneck: no issue


कार्य पूर्ण -- as on 07-May-2024

Physical Peramenters

Particulars Sanction Resanction Upto Last Fy For Cfy 2024-2025
Remaining Target Achievement
Length of Road [Km] 10 10 10.000 0 0.000 0.000
Currently only Bank Gaurantee information is avilable