Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 4.7 | 4.7 | 0.000 | 4.7 | 4.700 | 3.500 |
43W1031 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : e file 48456 dt 15-01-2024
TS Amount (lakhs) : 127.73 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
127.73
Resanction Cost :
127.73
Tentative Cost :
127.73
Exp. Upto Last Fy : 0.59
For CFY 2024-2025
Remaining : 127.14
Demand : 127.14
Allotment : 80.00
Exp in CFY : 43.54
Total Up to Date Exp : 44.13
Construction Started
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 75 %
Sanction on :
6 months 2 days ago
15 Jan 2024
Tentative Completion date:
3 months 1 week from now
31 Oct 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
पी सी एवम् अन्य निर्माण कार्य प्रगति पर । -- as on 04-Jun-2024
Physical Peramenters