Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 7 | 7 | 0.000 | 7 | 7.000 | 7.000 |
43W1032 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : e file 48456 dt 15-01-2024
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
206.23
Resanction Cost :
206.23
Tentative Cost :
206.23
Exp. Upto Last Fy : 0.00
For CFY 2024-2025
Remaining : 206.23
Demand : 206.23
Allotment : 0.00
Exp in CFY : 188.82
Total Up to Date Exp : 188.82
Work completed
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 100 %
Sanction on :
6 months 2 days ago
15 Jan 2024
Tentative Completion date:
1 week 18 hours from now
25 Jul 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
पी0सी0 का कार्य पूर्ण अन्य कार्य प्रगति पर है। -- as on 28-Jun-2024
Physical Peramenters