Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1 | 1 | 0.000 | 1 | 1.000 | 1.000 |
43W1034 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : e file 36639/12 dt 10-01-2024
TS Amount (lakhs) : 143.18 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
143.18
Resanction Cost :
143.18
Tentative Cost :
143.18
Exp. Upto Last Fy : 0.00
For CFY 2024-2025
Remaining : 143.18
Demand : 100.00
Allotment : 100.00
Exp in CFY : 77.32
Total Up to Date Exp : 77.32
Work completed
Physical Progress:
At start of FY 2024-2025 : 10 %
Up to Date : 95 %
Sanction on :
6 months 1 week ago
10 Jan 2024
Tentative Completion date:
3 weeks 5 days from now
13 Aug 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
अतिरिक्त पहाड कटान एवं चैडीकरण कार्य पूर्ण । पी0सी0 कार्य पूर्ण शेष कार्य प्रगति पर । -- as on 15-Jul-2024
Physical Peramenters