Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3.575 | 3.575 | 0.000 | 3.575 | 1.500 | 0.600 |
43W1037 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : e file 51381/13 dt 01-09-2023
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
126.19
Resanction Cost :
126.19
Tentative Cost :
126.19
Exp. Upto Last Fy : 3.52
For CFY 2024-2025
Remaining : 122.67
Demand : 80.00
Allotment : 30.00
Exp in CFY : 14.75
Total Up to Date Exp : 18.27
Construction Started
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 20 %
Sanction on :
5 months 4 weeks ago
19 Jan 2024
Tentative Completion date:
8 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
चैनेज 0/22 में कार्य प्रगति पर । -- as on 19-Jun-2024
Physical Peramenters