Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1.6 | 1.6 | 0.000 | 1.6 | 1.600 | 0.000 |
43W1048 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : e file 37809 dt 14-03-2024
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
60.04
Resanction Cost :
60.04
Tentative Cost :
60.04
Exp. Upto Last Fy : 0.00
For CFY 2024-2025
Remaining : 60.04
Demand : 35.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 0.00
none
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 0 %
Sanction on :
4 months 3 days ago
14 Mar 2024
Tentative Completion date:
8 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य हेतु निविदा आमत्रित। अनुवन्ध गठन की कार्यवाही गतिमान है । -- as on 12-Jul-2024
Physical Peramenters