Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 20 | 10.12 | 0.000 | 10.12 | 0.000 | 0.000 |
43W231 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0 सं0 4331/111(2)/12-08(मु0मं0घो0)/2012 दि0 26.10.12
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
251.60
Resanction Cost :
251.60
Tentative Cost :
251.60
Exp. Upto Last Fy : 191.62
For CFY 2024-2025
Remaining : 59.98
Demand : 10.00
Allotment : 0.00
Exp in CFY : 1.77
Total Up to Date Exp : 193.39
Alignment Approved
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 0 %
Sanction on :
11 years 8 months ago
26 Oct 2012
Tentative Completion date:
8 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
प्रfतकर fवतरण कार्य प्रगfत पर है । -- as on 16-May-2024
Physical Peramenters