Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 5 | 3.12 | 1.250 | 1.87 | 0.400 | 0.000 |
43W28 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेन संख्या - 2503/111-2/06 -37(प्रा0आ0)/06 दिनांक 20.06.2006
TS Amount (lakhs) : 57 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
81.00
Resanction Cost :
81.00
Tentative Cost :
81.00
Exp. Upto Last Fy : 26.33
For CFY 2024-2025
Remaining : 54.67
Demand : 10.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 26.33
Construction Started
Physical Progress:
At start of FY 2024-2025 : 40 %
Up to Date : 62 %
Sanction on :
18 years 3 weeks ago
20 Jun 2006
Tentative Completion date:
8 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: Other Reason
1.25 किमी0 में पहाड कटान पूर्ण । आगे विवाद होने के कारण कार्य रूका हुआ है । ग्रामवासियों द्वारा भूमि देने की सहमति नही बन रही है ं सहमति बनाने का प्रयास किया जा रहा है । -- as on 14-Jun-2021
Physical Peramenters