Work Profile Report [43W28]
Tenders
Aggrements
Project Activities
alerts
Samples
Administrative Approval Detail : शासनादेन संख्या - 2503/111-2/06 -37(प्रा0आ0)/06 दिनांक 20.06.2006
TS Amount (lakhs) : 57 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
81.00
Resanction Cost :
81.00
Tentative Cost :
26.33
Saving
54.67
Exp. Upto Last Fy :
26.33
For CFY 2025-2026
Remaining :
54.67
Demand :
0.00
Allotment :
1.49
Exp in CFY :
1.49
Total Up to Date Exp :
27.82
Work deferred
Sanction on : 19 years 2 weeks ago
20 Jun 2006
Physical Progress:
At start of FY 2025-2026 :
62 %
Up to Date :
62 %
Tentative Completion date on : 8 months 3 weeks from now
31 Mar 2026
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
पूर्व में यह मार्ग टिहरी प्रतापनगर मो0 मार्ग एवं धारकोट बंगद्वारा मो0 मार्ग से जुडा है। -- as on 23-Apr-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand