Work Profile Report [43W30]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शा0 सं0 2228/111(2)/06-60 (प्रा0आ0)/05 टी0सी0 दि0 2.9.2006
TS Amount (lakhs) : 81 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
81.00
Resanction Cost :
207.52
Tentative Cost :
81.00
Saving
126.52
Exp. Upto Last Fy :
88.57
For CFY 2024-2025
Remaining :
118.95
Demand :
35.00
Allotment :
25.00
Exp in CFY :
64.26
Total Up to Date Exp :
152.84
Construction Started
Sanction on : 18 years 2 months ago
02 Sep 2006
Physical Progress:
At start of FY 2024-2025 :
20 %
Up to Date :
60 %
Tentative Completion date on : 3 months 3 days from now
27 Feb 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
किमी0 5 में पहाड कटान कार्य प्रगति पर । -- as on 24-Oct-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: