Administrative Approval Detail : शा0 सं0 2228/111(2)/06-60 (प्रा0आ0)/05 टी0सी0 दि0 2.9.2006
TS Amount (lakhs) : 81 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
81.00
Resanction Cost :
207.52
Tentative Cost :
207.52
Exp. Upto Last Fy :
88.57
For CFY 2024-2025
Remaining :
118.95
Demand :
85.00
Allotment :
88.59
Exp in CFY :
72.59
Total Up to Date Exp :
161.16
Construction Started
Sanction on : 18 years 3 months ago
02 Sep 2006
Physical Progress:
At start of FY 2024-2025 :
20 %
Up to Date :
70 %
Tentative Completion date on : 2 months 2 days from now
27 Feb 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
Overall Saving 126.52 has been recorded as expected cost of work reduced from 207.52 to 81 . -- as on 06-Dec-2024