Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 5 | 5 | 5 | 0 |
43W323 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0 सं0 1152/111(2)/14-62 (प्रा0आ0)/2013 दि0 21.02.2014
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
51.03
Resanction Cost :
51.03
Tentative Cost :
51.03
Exp. Upto Last Fy : 0.23
For CFY 2024-2025
Remaining : 50.80
Demand : 20.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 0.23
Unstarted Work
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 0 %
Sanction on :
10 years 4 months ago
21 Feb 2014
Tentative Completion date:
8 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
परन्तु समरेखण में बांज का जंगल होने के कारण सहा0 अभि0 द्वारा दि0 14.7.15 को पुनः अन्य समरेखण पर सहमति हेतु प्रधान को पत्र लिखा गया है । विवाद उत्पन्न।
Physical Peramenters