Work Profile Report [43W327]

जनपद टिहरी के विधानसभा प्रतापनगर में दूयूली वैण्ड म्ंयूडी मंदार मिसिंग लिंक का निर्माण
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Remarks
  • Tenders

    Aggrements

    Project Activities

    alerts

    Documents

    Samples

Administrative Approval Detail : शा0 सं0 1152/111(2)/14-62 (प्रा0आ0)/2013 दि0 21.02.2014

TS Amount (lakhs) : 0 Lacs

Budget Financial Head : State Sector ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

54.99

Resanction Cost :

54.99

Tentative Cost :

54.99

Exp. Upto Last Fy :

49.14

For CFY 2024-2025

Remaining :

5.85

Demand :

3.00

Allotment :

0.31

Exp in CFY :

0.31

Total Up to Date Exp :

49.45

Phase1 DPR Submitted

Sanction on : 10 years 10 months ago

21 Feb 2014

Physical Progress:

At start of FY 2024-2025 :

0 %

Up to Date :

95 %

Tentative Completion date on : 3 months 6 days from now

31 Mar 2025

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2024-2025
Remaining
Target
Achievement
Road [Km]
5
3.72
3.72
-

Remark

view all

प्रतिकर वितरण कार्य पूर्ण। -- as on 06-Dec-2024

Rating : 100

No Forest Case in The Work

No Hindrance / Bottleneck

Assets :

Work not linked with IM

Bridges on The Basis of AI: