Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 5 | 3.72 | 3.72 | 0 |
43W327 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0 सं0 1152/111(2)/14-62 (प्रा0आ0)/2013 दि0 21.02.2014
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
54.99
Resanction Cost :
54.99
Tentative Cost :
54.99
Exp. Upto Last Fy : 49.14
For CFY 2024-2025
Remaining : 5.85
Demand : 3.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 49.14
Construction Started
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 0 %
Sanction on :
10 years 4 months ago
21 Feb 2014
Tentative Completion date:
8 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
प्रतिकर वितरण कार्य प्रगति पर है । -- as on 16-May-2024
Physical Peramenters