Work Profile Report [43W35]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शा0 सं0 764/111 (2)/08 - 65 /07 (प्रा0 आ0 ) दि0 24.3.08
TS Amount (lakhs) : 139 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
140.00
Resanction Cost :
140.00
Tentative Cost :
140.00
Exp. Upto Last Fy :
130.87
For CFY 2024-2025
Remaining :
9.13
Demand :
9.13
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
130.87
Construction Started
Sanction on : 16 years 9 months ago
24 Mar 2008
Physical Progress:
At start of FY 2024-2025 :
0 %
Up to Date :
93 %
Tentative Completion date on : 3 months 6 days from now
31 Mar 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
किमी0 2 में पहाड कटान कार्य पूर्ण अग्रिम भाग में पहाड कटान कार्य प्रगति पर । -- as on 07-Dec-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand