Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 5 | 5.5 | 4.000 | 1.5 | 1.500 | 1.200 |
43W558 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0 सं0 89/लो0नि0-01/04 प्रा0आ0/04 दि0 06.02.2004 एवं शा0 सं0 15मेमो /111(2)/20 /07 प्रा0आ0/2019 दि0 13.03.2020
TS Amount (lakhs) : 346.16 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
69.50
Resanction Cost :
346.16
Tentative Cost :
346.16
Exp. Upto Last Fy : 181.21
For CFY 2024-2025
Remaining : 164.95
Demand : 120.00
Allotment : 0.00
Exp in CFY : 2.21
Total Up to Date Exp : 183.42
Construction Started
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 80 %
Sanction on :
20 years 5 months ago
06 Feb 2004
Tentative Completion date:
8 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
चै0 5/5 तक पहाड कटान कार्य पूर्ण । किमी0 4 तक पार्ट द्वितीय कार्य पूर्ण। शेष कार्य प्रगति पर । -- as on 15-Jul-2024