Work Profile

भागीरथीपुरम खेमडा कुण्डाली मो0 मार्ग


Work not linked with IM

Bridges on The Basis of AI:

Administrative Approval Detail : शा0 सं0 89/लो0नि0-01/04 प्रा0आ0/04 दि0 06.02.2004 एवं शा0 सं0 15मेमो /111(2)/20 /07 प्रा0आ0/2019 दि0 13.03.2020

TS Amount (lakhs) : 346.16 Lacs

Financial Detail (in Rs Lakhs)

Sanction Cost :

69.50

Resanction Cost :

346.16

Tentative Cost :

346.16

Exp. Upto Last Fy : 181.21

For CFY 2024-2025

Remaining : 164.95

Demand : 120.00

Allotment : 0.00

Exp in CFY : 2.21

Total Up to Date Exp : 183.42

Construction Started

Physical Progress:

At start of FY 2024-2025 : 0 %

Up to Date : 80 %

Sanction on :
20 years 5 months ago
06 Feb 2004


Tentative Completion date:
8 months 1 week from now
31 Mar 2025


Actual Completion Date:
Not Yet Reported


Rating : 86

Remark

Bottelneck: no issue


चै0 5/5 तक पहाड कटान कार्य पूर्ण । किमी0 4 तक पार्ट द्वितीय कार्य पूर्ण। शेष कार्य प्रगति पर । -- as on 15-Jul-2024

Physical Peramenters

Particulars Sanction Resanction Upto Last Fy For Cfy 2024-2025
Remaining Target Achievement
Length of Road [Km] 5 5.5 4.000 1.5 1.500 1.200
Currently only Bank Gaurantee information is avilable