Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3.6 | 3.6 | 3.600 | 0 | 0.000 | 0.000 |
43W573 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0 स0 2206/111(2)/16-12(एमएलए)/2016 दि0 25.07.2016
TS Amount (lakhs) : 207.61 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
207.61
Resanction Cost :
207.61
Tentative Cost :
207.61
Exp. Upto Last Fy : 157.71
For CFY 2024-2025
Remaining : 49.90
Demand : 49.90
Allotment : 16.21
Exp in CFY : 0.81
Total Up to Date Exp : 158.52
Construction Started
Physical Progress:
At start of FY 2024-2025 : 80 %
Up to Date : 85 %
Sanction on :
7 years 11 months ago
25 Jul 2016
Tentative Completion date:
3 weeks 6 days from now
14 Aug 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
पहाड कटान का कार्य पूर्ण । पार्ट द्वितीय का कार्य प्रगति पर । 3.60 किमी0 में पहाड कटान पूर्ण एवं 2.60 किमी0 पार्ट द्वितीय कार्य पूर्ण। शेष 1.00 किमी0 में चैनेज 4.00 में पार्ट द्वितीय प्रगति पर । -- as on 13-Jun-2024
Physical Peramenters