Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3.6 | 3.6 | 3.600 | 0 | 0.000 | 0.000 |
43W573 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0 स0 2206/111(2)/16-12(एमएलए)/2016 दि0 25.07.2016
TS Amount (lakhs) : 207.61 Lacs
Financial Detail
Sanction Cost : 207.61 Lacs
Resanction Cost : 207.61 Lacs
Exp. Upto Last Fy : 157.71 Lacs
For CFY 2024-2025
Remaining : 49.90 Lacs
Demand : 49.90 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 157.71 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 80 %
Up to Date : 80 %
Sanction on :
7 years 9 months ago
25 Jul 2016
Tentative Completion date:
2 months 3 weeks from now
14 Aug 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
पहाड कटान का कार्य पूर्ण । पार्ट द्वितीय का कार्य प्रगति पर । -- as on 06-Mar-2024