Work Profile Report [43W574]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शा0 स0 2206/111(2)/16-12(एमएलए)/2016 दि0 25.07.2016
TS Amount (lakhs) : 297.58 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
297.58
Resanction Cost :
297.58
Tentative Cost :
295.50
Saving
2.08
Exp. Upto Last Fy :
295.02
For CFY 2024-2025
Remaining :
2.56
Demand :
2.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
295.02
Work completed
Sanction on : 8 years 4 months ago
25 Jul 2016
Physical Progress:
At start of FY 2024-2025 :
100 %
Up to Date :
100 %
Tentative Completion date on : 1 year 2 months ago
15 Oct 2023
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
Overall Saving 2.08 has been recorded as expected cost of work reduced from 297.58 to 295.5 . -- as on 10-Nov-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand