Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1 | 1 | 0.500 | 0.5 | 0.500 | 0.500 |
43W580 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0 स0 2207/111(2)/16-12(एमएलए)/2016 दि0 26.07.2016
TS Amount (lakhs) : 60.35 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
60.35
Resanction Cost :
60.35
Tentative Cost :
60.35
Exp. Upto Last Fy : 51.26
For CFY 2024-2025
Remaining : 9.09
Demand : 9.09
Allotment : 0.00
Exp in CFY : 1.99
Total Up to Date Exp : 53.25
Work completed
Physical Progress:
At start of FY 2024-2025 : 50 %
Up to Date : 100 %
Sanction on :
7 years 11 months ago
26 Jul 2016
Tentative Completion date:
2 weeks 3 days ago
30 Jun 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण दायित्व शेष। -- as on 12-Jul-2024
Physical Peramenters