Work Profile Report [43W584]
Tenders
Project Activities
alerts
Samples
Administrative Approval Detail : शा0 स0 2207/111(2)/16-12(एमएलए)/2016 दि0 26.07.2016
TS Amount (lakhs) : 162.85 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
162.85
Resanction Cost :
162.85
Tentative Cost :
162.85
Exp. Upto Last Fy :
155.36
For CFY 2024-2025
Remaining :
7.49
Demand :
7.49
Allotment :
1.50
Exp in CFY :
1.27
Total Up to Date Exp :
156.64
Work completed
Sanction on : 8 years 4 months ago
26 Jul 2016
Physical Progress:
At start of FY 2024-2025 :
0 %
Up to Date :
100 %
Tentative Completion date on : 1 year 11 months ago
31 Dec 2022
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य पूर्ण दायित्व शेष। -- as on 12-Jul-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand