Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3.15 | 3.15 | 3.15 | 0 |
43W584 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0 स0 2207/111(2)/16-12(एमएलए)/2016 दि0 26.07.2016
TS Amount (lakhs) : 162.85 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
162.85
Resanction Cost :
162.85
Tentative Cost :
162.85
Exp. Upto Last Fy : 155.36
For CFY 2024-2025
Remaining : 7.49
Demand : 7.49
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 155.36
Work completed
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 100 %
Sanction on :
7 years 11 months ago
26 Jul 2016
Tentative Completion date:
1 year 6 months ago
31 Dec 2022
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण दायित्व शेष। -- as on 12-Jul-2024